Skip to main content
Back to Microcement – Nikkolor Cemento 3D Structured Finish – 20 kg

Revision 11 | September 2026 application standard

Cemento 3DFine structured nanocement for flat and sculptural mineral finishes

Select the actual substrate, complete its release and preparation procedure, confirm the labelled build-up, then execute the product method in order.

Source: Nikkolor Australia · Cemento 3D Australian Technical Data Sheet · Revision 11 | September 2026

Download Rev 11 TDS

The supplied Revision 11 sheets and Revision 5 manual remain the owner-current source set, with further supplier review pending. The field method also reflects later owner direction on compression, limited detail sanding and Decor Finish suitability (walls and dry interior floors only without a slip-resistance additive, subject to existing wall exposure restrictions). Additive identity, dosage, tested rating and approved additional uses remain unconfirmed; adding it does not automatically approve wet floors or exterior use. These are owner corrections, not rewritten supplier evidence; the approved original PDFs remain unchanged.

Before selection

Non-negotiable controls

01

Moisture release

There is no universal percentage release gate. Establish the applicable moisture acceptance criterion for the actual substrate and project, then record the calibrated instrument, test method, units, substrate, test locations, environmental conditions and results. Visible dryness or elapsed time alone is not approval to proceed.

02

Substrate-driven reinforcement

Select primer, receiving layer and fibreglass mesh from the actual substrate and condition. Mesh is used where screeds, repairs, chases, board joints or transitions require reinforcement; it is not automatic merely because a substrate is tiled and does not replace crack-isolation or movement-joint treatment.

03

Wet areas and membranes

The Nikkolor system is not a waterproofing membrane. Confirm membrane identity, cure, surface condition and compatibility, and do not add primer, mesh or another layer over a membrane unless that complete interface is approved. Without a slip-resistance additive, Decor Finish is only for walls and dry interior floors, subject to existing wall exposure restrictions. Bathrooms and showers are not automatically approved. An additive adds slip resistance but its name, dosage, tested rating and approved additional uses remain unconfirmed; it does not automatically approve wet floors or exterior use.

04

Stop-work rule

If the substrate, exposure or interface is not covered by current Nikkolor documentation, stop and obtain project-specific technical direction before coating. Apply only while the substrate is above +10°C and all other product/environment limits are met; the stricter condition governs. Performance evidence belongs only to the exact tested complete build-up and must not be transferred to another primer, protection system, substrate or Australian classification.

01 / substrate

What are you applying over?

Select the actual receiving surface, not the desired finish.

Selected substrate / Rev 11 p. 4

Existing ceramic / porcelain tile

Complete in order. Do not apply the next stage until it is visibly dry and meets the documented criterion applicable to the actual substrate and project. Record instrument, method, units, substrate, locations, conditions and results.

Release checks & preparation

Release check

Tap-test the full area and mark hollow, drummy, loose or cracked tiles.

Release check

Check grout lines, perimeter joints and movement joints for recurring movement.

Release check

Identify wax, soap, silicone, grease, cleaners or sealers that can prevent adhesion.

Release check

Check falls, ponding and any moisture source behind or beneath the tiled assembly.

Preparation sequence

  1. 1Remove every loose or drummy tile and rebuild the void with a compatible repair material.
  2. 2Degrease thoroughly, rinse as required and allow the surface to dry.
  3. 3Mechanically abrade the glaze to a uniform keyed finish without destabilising the installation.
  4. 4Vacuum completely. Fill deep grout lines and irregularities; allow repairs to cure and sand flat.
  5. 5Preserve all required movement joints. Never bridge an active joint with decorative material.
  6. 6Select any fibreglass mesh and primer or receiving layer from the actual substrate and condition; record the approved decision before coating.

02 / specified build-up

Cemento 3D

Decor Finish - 3 coatsCemento 3D coat 2Cemento 3D coat 1Primer Beton - receiving layerExisting ceramic / porcelain tile…PER-LAYER THICKNESS REFERENCES1. Decor Finish - 3 coatsReference: ≈ 0.08 mm per coat — wet estimate2. Cemento 3D coat 2Reference: ≈ 0.54 mm per coat — wet estimate3. Cemento 3D coat 1Reference: ≈ 0.54 mm per coat — wet estimate4. Primer Beton - receiving layerReference: ≈ 1.50 mm per coat5. Existing ceramic / porcelain tile substrateReference: Project-specific — thickness notspecifiedSource: Owner-supplied Nikkolor product thickness guideGuide note: Guide values, not measured cured thicknesses. Do not sum wet estimates; measure a fully curedcomplete-system sample for finished levels and interfaces.Measurements are in millimetres, per coat unless stated otherwise. Wet estimates are calculated fromcoverage and are not confirmed cured thicknesses. Actual build-up varies with substrate, texture andapplication technique. Do not add wet estimates to determine finished levels; measure a fully curedsample of the complete system for floor levels, trims and adjoining surfaces.Measurements are in millimetres, per coat unless stated otherwise. Wet estimates are calculated from coverage and are not confirmed cured thicknesses. Actual build-up varies with substrate, texture and application technique. Do not add wet estimates to determine finished levels; measure a fully cured sample of the complete system for floor levels, trims and adjoining surfaces.

Build-up, bottom to top

  1. 1.Existing ceramic / porcelain tile substrate
  2. 2.Primer Beton - receiving layer
  3. 3.Cemento 3D coat 1
  4. 4.Cemento 3D coat 2
  5. 5.Decor Finish - 3 coats

System status

For sound ceramic, porcelain or marble. Use Primer NK before Primer Beton where absorbed contamination risk is identified and testing supports it. Decor Finish without a slip-resistance additive is limited to walls and dry interior floors, subject to project wall exposure approval; substrate selection alone does not approve wet floors or exterior use.

Rev 11 method and substrate references / pp. 4 · 5 · 6 · 7 · 8 · 9 · 10 · 4

Release gate

Do not start while any of these remain

  • Loose or drummy tiles
  • moving cracks
  • silicone contamination
  • active moisture
  • failed waterproofing
  • uncontrolled movement joint

03 / application method

Numbered field method

Complete each step in order. Timing references are given at +20°C unless the governing technical data sheet states otherwise.

  1. 01

    Release the substrate after confirming its precise type, condition, expected exposure and protection requirement. Resolve instability, movement, moisture, waterproofing and flatness defects before decorative work.

  2. 02

    Select the substrate-specific primer, receiving layer and any fibreglass reinforcement. Record those decisions in the project QA documents; do not use a universal build-up.

  3. 03

    Measure approximately 300 mL potable water per kg of powder (approximately 6 L for a 20 kg pack). The formula toner is additional: never subtract its volume from the water. Keep water, toner, equipment and mixing time consistent between batches.

  4. 04

    Homogenise the shade-specific Nikkolor toner. Use the sequence water → toner → mix to uniform colour → gradually add powder while mechanically mixing. Scrape the sides and base, then remix to a smooth, homogeneous, lump-free paste.

  5. 05

    Use the mixed material within its approximate 4-hour pot life at +20°C. Never retemper material that has begun to stiffen.

  6. 06

    Apply the substrate-specific primer or receiving layer and allow it to dry as stated in its current TDS. Where Primer Beton is specified, matching or closely matching it to the Cemento 3D colour is recommended, especially on floors, to reduce white chip contrast and assist blending; it does not prevent chips or guarantee an invisible repair.

  7. 07

    Apply the first Cemento 3D coat with a stainless-steel trowel. Allow approximately 12 hours at +20°C, subject to actual drying and the recorded, substrate-appropriate release criterion.

  8. 08

    Apply the second Cemento 3D coat. Allow approximately 24 hours at +20°C before protection, subject to actual drying and the recorded, substrate-appropriate release criterion.

  9. 09

    Finish primarily by controlled trowel compression, with careful hand detailing of corners while the material is workable, and minimise later sanding. Sanding is not a general finishing step. If an isolated detail still requires refinement, wait at least 24 hours at +20°C, then use P150 or P180 only on the affected detail. Trial the method on a sample, preserve thickness, texture, colour and continuity, stop if the coating smears or the abrasive loads, and compatibly extract and remove all dust.

  10. 10

    Owner-approved guidance: without a slip-resistance additive, Decor Finish is only for walls and dry interior floors. Wall exposure, substrate and complete-system restrictions still apply; this is not blanket approval for shower walls or exterior walls. An additive adds slip resistance, but its product name, dosage, tested rating and approved additional uses are unconfirmed. Do not assume an additive approves wet floors, shower floors or exterior use, or establishes an AS 4586 class. Obtain a written project-specific specification for other exposure. PRP remains a separate protection system governed by its own current TDS and project specification. Only for an approved wall exposure or dry interior floor, apply Decor Finish - 3 coats by short-pile roller, allowing approximately 24 hours between coats and 72 hours protected drying after the final coat at +20°C. For white or very light shades, use Semi-Gloss first, then the specified Matte or selected sheen for the remaining coats.

  11. 11

    Protect the completed work. At +20°C, light walkability is approximately 48 hours subject to completed protection and handover controls, hardening approximately 7 days, furniture approximately 10 days and full cure approximately 28 days. After the final Decor coat provide 72 hours protected drying; throughout the first week keep the surface dry, do not clean it and avoid general or preventable traffic. Never drag furniture. Dry does not mean cured. PRP and special-service release instead follow the complete current PRP TDS and project specification.

Hold point checks

Pass before the next coat

Substrate release

Proceed
Sound, stable, clean, correctly cured and permanently dry; required interfaces and movement details approved.
Hold work
Weakness, movement, moisture, contamination, incompatible residue or an unapproved interface remains.

Batch control

Proceed
Measured potable water, homogenised shade-specific toner, consistent equipment and mixing; smooth lump-free paste within pot life.
Hold work
Guessed water or toner, contamination, lumps, stiffening or retempering.

Decorative recoat

Proceed
Previous layer is visibly dry and meets the documented substrate- and project-appropriate criterion; instrument, method, units, substrate, locations, conditions and results are recorded.
Hold work
The applicable criterion is undefined or unmet, visible dampness remains, records are incomplete, or elapsed time is the only evidence.

Finish refinement

Proceed
The finish is closed by controlled trowel compression; any sanding is limited to an isolated detail after the specified drying period, then dust is removed completely.
Hold work
General finish sanding, burn-through, contamination, unintended flattening, patchy polishing or an unapproved finish.

Protection and release

Proceed
Protection suits the service condition and its current TDS; cure and handover restrictions are recorded.
Hold work
Wrong protection, incomplete coats, trapped moisture or early traffic, water, cleaning or furniture exposure.

Hands-on learning

Build practical capability

Lux Academy provides practical instruction in assessment, material handling and application technique. Project-specific support remains important after training.